Can I set GoAnywhere to run just one concurrent job?
Can I set GoAnywhere to run just one concurrent job?
- Move the cursor over the Administration menu.
- Select the Global Setting menu option.
- Under Global Settings click on the Runtime tab
- Change the Maximum pool size to 1.
- Click the save button.
- Restart GoAnywhere.
Note: This will only limit projects that are submitted in batch mode. It is still possible to run multiple projects concurrently by executing them interactively. i.e. If the [Execute Project] button of a project is clicked while another project is running in batch, it would be possible to have both projects running.
For information on how to stop & start GoAnywhere view the following topic:
http://www.goanywheretoday.com/forum/viewtopic.php?f=19&t=35&p=35
- Support_Duane
- Support Specialist
- Posts: 66
- Joined: Thu Mar 05, 2009 2:49 pm
Who is online