Multiple modules conditionally executed per variable value

Looking for an example project to get you started?

Multiple modules conditionally executed per variable value

Postby Support_Steve » Mon Apr 06, 2009 10:47 am

In GoAnywhere you can specify multiple modules in a project. Some of these modules could be used for error processing while others can be used for organizing tasks. In the example below I have specified a project level variable called FirstOrSecond. If that variable is set to a 1 the "First" module will execute. If it is set to a 2 the "Second" module will execute.

When GoAnywhere executes this project by default it will begin with the Main module. On the Main module I've added a couple modules to the Depends On attribute which are separated by a comma. Since the Main module depends on First and Second to run it will then pass control to the First module. I added a Execute Only If condition on that module to say to run only when the variable is set to a 1. I've also added conditional logic to the Second module to run only if it's a 2.

In the example below the "First" module will execute because the variable is set to a 1. The "Second" module will be skipped and then the "Main" module will finish execution. For demonstration purposes each module only prints some static text.

Code: Select all
<project name="Multiple Modules" mainModule="Main" version="1.0">
   <description></description>
   <module name="Main" dependsOn="First,Second">
      <print>
         <![CDATA[Main module printing]]>
      </print>
   </module>
   <module name="First" if="FirstOrSecond eq 1">
      <print>
         <![CDATA[First half printing]]>
      </print>
   </module>
   <module name="Second" if="FirstOrSecond eq 2">
      <print>
         <![CDATA[Second half printing]]>
      </print>
   </module>
   <variable name="FirstOrSecond" value="1" />
</project>


With this in place I can easily override the project variable at run time (via GoAnywhere's scheduler, Execute Advanced screen, RUNPROJECT command, etc) and determine what tasks will be executed.